6. MATERIAL
6.1 All rolls of Altro Safety Flooring must be stored in an upright position. Ensure that rolls are secured against accidental damage and that of falling over.
6.2 Ensure that all sufficient rolls allowed are delivered and stored within the appropriate area for a minimum of 24 hours prior installation.
6.3 Screw into sub floor using countersunk stainless steel screws.
6.4 Ensure a clean, flat, dry and well lighted area be allowed to lay material out prior to cutting appropriate lengths.
6.5 Unwrap and unroll material face down on the prepared cutting area.
6.6 Using straight edge and square ensure that leading edge is cut straight and true.
6.7 Mark clearly on back of material a direction arrow. It is imperative that all subsequent cuts from all rolls are marked in the same direction.
6.8 All cuts shall be cut oversize by 25mm each end.
6.9 Align straight edge at 90 degrees to salvage edge utilising square at required length. Cut and mark as #1.
6.10 Cut subsequent lengths. Mark directional arrow and consecutive numbers eg. 1,2,3,4,5 etc
6.11 Roll all cuts and place in a standing position within the area to be laid for a minimum of 24 hours prior to installation. This will allow material to acclimatize to the temperature of the installation area.